Introduction
As a DM approved demolition contractor in Dubai, Al Zelzal Demolition Works LLC handles complete demolition permit coordination, including telecom approvals from e& (Etisalat) and du.
These approvals are part of the Dubai Municipality demolition permit workflow, and the final permit is issued only after all authority approvals are completed in the system.
📞 Call / WhatsApp: 056 780 0464 for demolition NOC support in Dubai.
Dubai Municipality Application Portal
All demolition applications must be submitted through the official Dubai Municipality portal:
The DM system routes the application automatically to all relevant authorities, including Etisalat and Du, for approval and verification.
👉 For full compliance understanding, see:
Dubai demolition permit process 2026
https://zelzaldemolition.com/dubai-demolition-permit-process
DM Approval Workflow (Important)
Once the application is submitted:
-
Etisalat NOC is uploaded from contractor portal
-
Du approval is processed inside DM system
-
All approvals are re-verified in DM portal
-
Authorities may validate documents again during review
In most cases, no additional documents are requested after submission.
Final demolition permit is issued only after full approval confirmation.
Etisalat (e&) NOC for Demolition Dubai
Application Channel
https://www.gis4me.ae/enoc/etisalat/portal
-
Contractor only portal
-
Owner cannot apply
Required Documents
-
Dubai Municipality appointment letter
-
DM demolition application form or Etisalat Application form
-
e& (Etisalat) disconnection letter
-
Approved demolition drawings
-
Site photos including telecom equipment/device photos
Inspection Process
-
Inspection is mandatory and must be physically conducted on site
-
Etisalat team must visit before approval
-
Site must be fully vacant before inspection
-
Approval is issued only after inspection clearance
Etisalat NOC Timeline: 7–18 Working Days
Cable Handling Rule
If telecom infrastructure is found:
-
e& (Etisalat) handles removal or relocation
-
Contractors do not touch telecom assets
-
Work continues only after clearance
Important Note
Even after approval is issued:
-
DM system may re-check documents
-
Clarification may be requested during DM review stage
-
This is system validation, not re-application
Du NOC for Demolition Dubai
When Required
The du NOC is required only in selected areas where Du infrastructure exists and is triggered within the Dubai Municipality workflow.
DM System Process
For all demolition applications:
-
Du approval is processed inside DM system
-
No separate public link exists
-
Approval is reflected directly in DM portal
Inspection Process
-
Du may conduct inspection only in specific cases
-
Site visit depends on infrastructure presence
-
Approval is issued through DM system after review
Trakhees Process
For Trakhees jurisdiction:
Email Du NOC team with:
-
Appointment letter
-
Demolition drawings
-
Affection plan
-
DU application form
Then:
-
Inspection is scheduled
-
Site visit is conducted
-
Approval is issued after inspection within 7 days.
Cable Handling Rule
If Du cable is found:
-
du handles protection or relocation
-
Contractors do not interfere
-
Approval is issued after completion
Full Approval Flow
-
Apply through Dubai Municipality portal
https://www.dm.gov.ae/ -
Submit Etisalat NOC via contractor portal
https://www.gis4me.ae/enoc/etisalat/portal -
Mandatory Etisalat inspection
-
Etisalat approval issued and downloaded
-
Du approval processed inside DM system
-
All approvals re-verified in DM portal
-
Final demolition permit issued
Key Points
-
Etisalat NOC requires mandatory site inspection before approval
-
Du approval is part of DM system workflow
-
Both approvals are re-validated inside Dubai Municipality system
-
No major additional documents are usually required after submission
-
Final permit depends on full authority confirmation
FAQ
Is Du NOC required for all demolition plots in Dubai?
No. du NOC is required only where infrastructure exists or is triggered by Dubai Municipality system.
Is Etisalat NOC applied by property owner?
No. e& (Etisalat) NOC must be applied only through contractor portal after inspection.
Is DM portal the only official demolition application system?
Yes. All demolition applications must be submitted through https://www.dm.gov.ae/ which routes approvals to all authorities.
Conclusion
Etisalat and Du approvals are mandatory parts of Dubai demolition permit workflow.
-
e& (Etisalat) approval is issued after contractor portal inspection
-
du approval is processed inside Dubai Municipality system
-
Both approvals are re-verified before final permit release
-
Etisalat timeline: 7–18 working days
-
Final demolition permit is issued only after full authority confirmation
Call 056 780 0464 — Al Zelzal Demolition Works LLC, DM Approved Demolition Contractor Dubai.
Add comment
Comments